REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: August 1, 2016
FROM: MICHAEL CARBAJAL, Division Manager
Public Utilities Department
SUBJECT
..Title
Approval of T-4 Downtown 3MG Water Storage Tank and Booster Pump Station Change Order No. 1
..Body
RECOMMENDATION
Approve
EXECUTIVE SUMMARY
[Brief, 1-2 paragraphs; information stated here must be expanded in Background section; clear and concise so anyone understands action being requested]
BACKGROUND
[Include: Any prior history; "City Attorney has reviewed and approved to form," if applicable; source of funding; appropriate regulation summary information]
ENVIRONMENTAL FINDINGS
[Include CEQA findings or state N/A]
LOCAL PREFERENCE
[N/A due to State and Federal money; N/A because it is more than 1/2 of 1%; or yes, state why]
FISCAL IMPACT
[Funding source, clarify whether General Fund is or is not impacted; appropriation authority already approved or an AAR is attached; if appropriate explain impact on other projects or timing of funding from other agencies; future obligations]
Attachment: [If more than one, pluralize]
Patrocinadores
- Department of Public Utilities
Historial
Documentos adjuntos
- TML4_CO No 1_ Ready for Signatures.pdfscanned_image