Consideración del Mapa de Área Tentativa de Adquisición No. 6215/UGM y la Evaluación Ambiental relacionada No. T-6215/UGM, para la propiedad ubicada en la esquina suroeste de las Avenidas West Gettysburg y North Hayes (Distrito 1 del Consejo). 1. ADOPTAR la Declaración Negativa Mitigada preparada para la Evaluación Ambiental No. T-6215/UGM de fecha 10 de mayo de 2019 y la Adenda de fecha 13 de junio de 2019. 2. APROBAR el Mapa de Tracto Tentativo de Adquisición No. T-6215/UGM para una subdivisión residencial unifamiliar de 98 lotes sujeto al cumplimiento de las Condiciones de Aprobación del 19 de junio de 2019.
Traducido automáticamente. Es posible que parte del contenido aún no esté disponible en este idioma.
- Presentado por
- City Council
- Fecha
- Wed, Jun 19, 2019
- Resultado
- Wed, Jun 19, 2019
Texto completov1
REPORT TO THE PLANNING COMMISSION
June 19, 2019
FROM: MIKE SANCHEZ, Assistant Director
Development Services Division
THROUGH: WILL TACKETT, Supervising Planner
Development Services Division
BY: CHRIS LANG, Planner
Development Services Division
SUBJECT
..Title
Consideration of Vesting Tentative Tract Map No. 6215/UGM and related Environmental Assessment No. T-6215/UGM, for property located on the southwest corner of West Gettysburg and North Hayes Avenues (Council District 1).
1. ADOPT the Mitigated Negative Declaration as prepared for Environmental Assessment No. T-6215/UGM dated May 10, 2019 and the Addendum dated June 13, 2019.
2. APPROVE Vesting Tentative Tract Map No. T-6215/UGM for a 98-lot single family residential subdivision subject to compliance with the Conditions of Approval dated June 19, 2019.
..Body
EXECUTIVE SUMMARY
Bret Giannetta of Giannetta Engineering, on behalf of Ashlan & Hayes Investments LLC, has filed Vesting Tentative Tract Map No. 6215/UGM, pertaining to approximately 17.45 acres of property located on the southwest corner of West Gettysburg and North Hayes Avenues. Vesting Tentative Tract Map No. 6215 is a proposal to subdivide the property into a 98 lot single-family residential subdivision. Outlots A, B, and C are to be dedicated to the City of Fresno for Class 1 Bicycle and Pedestrian trail purposes, and Outlot D will be dedicated for future right of way and open space. Reduced lot sizes are being proposed and shall comply with Section 15-904-B of the Fresno Municipal Code (FMC), Enhanced Streetscape.
The subject property is located within the Fresno General Plan and the West Area Community Plan, and both plans designate the subject site for Medium Density Residential (5 to 12 dwelling units per acre) planned land uses. Thus, the subject application is consistent with the planned land use and zoning approved for the project site and will implement goals, objectives, and policies of the Fresno General Plan and the West Area Community Plan.
BACKGROUND / ANALYSIS
Bret Giannetta of Giannetta Engineering, on behalf of Ashlan & Hayes Investments LLC, has filed Vesting Tentative Tract Map No. 6215/UGM pertaining to approximately 17.45 acres of property
located on the southwest corner of West Gettysburg and North Hayes Avenues.
Vesting Tentative Tract Map No. 6215/UGM has been filed in order to subdivide the subject property for purposes of facilitating a 98 lot conventional single family residential development on the subject property.
The proposed project will require dedications for public street rights-of-way as well as the installation and construction of both public and private facilities and infrastructure in accordance with the standards, specifications and policies of the City of Fresno.
The existing RS-5/UGM (Residential Single Family, Medium Density/Urban Growth Management) zoning for the subject property and the proposed residential density of approximately 5.6 dwelling units per acre is consistent with the Medium Density Residential (5.0-12 dwelling units per acre) planned land use designation for the subject property.
The subject property is currently vacant and was annexed to the City of Fresno in 2006 as part of Annexation No. 1298.
The subject property was previously approved for subdivision and development in 2008 as part of Tentative Tract Map No. 5891/UGM, a 738-lot subdivision of approximately 122.93 acres of land comprising the majority of the quarter corner section located between North Bryan and North Hayes Avenues and West Ashlan and West Gettysburg Avenues. While the previously approved subdivision design has been abandoned and these lands have been sold into new ownership, the newly proposed subdivision design incorporates aggregate open space, pedestrian paths/paseos, trail facilities, and boundary streets, which will facilitate both vehicular and pedestrian connectivity for future development on adjacent lands and afford availability of open space amenities in order to facilitate a well-integrated and Complete Neighborhood for the area.
The proposed subdivision design will utilize elements of an "Enhanced Streetscape" for a portion of the subject property, which will allow application of the alternative development standards for single family residential development, as provided and defined within the City of Fresno Development Code.
The site is located within an area which is planned for urban residential uses and which has been substantially developed to the east with single family residences extending to Highway 99. Properties located directly to the north of the subject property remain primarily vacant, including an existing ponding basin. A subdivision directly to the west of the subject property is currently being developed with single family residential homes. Properties to the south of the subject property remain primarily vacant with the exception of several rural residences on the north side of West Ashlan Avenue.
Vehicular access points will be provided to West Gettysburg and North Olinda Avenue, with additional stubs to provide future connectivity with proposed or potential surrounding subdivisions. Two PG&E towers are existing and are to remain, with transmission wires running through the subject property. Proposed Outlots "A", "B" and "C" will be dedicated for Class 1 pedestrian/bicycle trail purposes and Outlot "D" will be dedicated for public open space and future right-of-way. Streets on either side of the outlots, North "D" and "E" Avenues, are proposed one-way streets. Outlot "E" is to be dedicated to the City for pedestrian access, and will provide additional connectivity to West Gettysburg Avenue.
Public Services
The Department of Public Utilities (DPU) has identified that adequate sanitary sewer and water services are available to serve the project site subject to implementation of the Fresno General Plan policies and the migration measures of the related Master Environmental Impact Report; and, the construction and installation of public facilities and infrastructure in accordance with Department of Public Works Standards, specifications and policies.
For sanitary sewer service these infrastructure improvements and facilities include typical requirements for construction and extension of sanitary sewer mains and branches. The proposed project will also be required to provide payment of sewer connection charges.
Implementation of the Fresno General Plan policies and the mitigation measures of the associated Master Environmental Impact Report, along with the implementation of the Water Resources Management Plan and the identified project related conditions of approval, which include water main extensions within the future West Gettysburg Avenue as well as the interior of the proposed tract. Installation of these services with meters to proposed residential lots will provide an adequate, reliable, and sustainable water supply for the project's urban domestic and public safety consumptive purposes.
According to the Fresno Metropolitan Flood Control District (FMFCD), the subject site is not located within a flood prone or hazard area. The Fresno Metropolitan Flood Control District has indicated that permanent drainage service will not be available; the District recommends temporary facilities until permanent service is available, however permanent facilities may also be constructed. Grading and drainage patterns are to direct drainage toward the southerly portions of the subject property, master plan facilities are planned for the future.
The City of Fresno Fire Department operates its facilities under the guidance set by the National Fire Protection Association in NFPA 1710, the Standard for the Organization and Deployment of Fire Suppression Operations, Emergency Medical Operations, and Special Operation to the Public by Career Fire Departments. NFPA 1710 sets standards for turnout time, travel time, and total response time for fire and emergency medical incidents, as well as other standards for operation and fire service. The Fire Department has established the objectives set forth in NFPA 1710 as department objectives to ensure the public health, safety, and welfare.
This project is currently within the service area for Fire Station 18. The Fire Department has reviewed this project to determine if it can be adequately served by Fire Personnel and Facilities consistent with NFPA 1710 Objectives. Based upon the current level of calls for service, the anticipated annual increase of calls for service of 11.28%, and the location of the temporary Fire Station 18 at a site that is not centrally located within the service area, the Fire Chief has determined that this project cannot be adequately served by existing Fire Facilities and Personnel, consistent with NFPA 1710 Objectives. Specifically, a 4 minute response time to fire calls in the Fire Station 18 service area is met only 39.96% of the time. In addition, truck response time in the service area does not meet the 8 minute standard. Instead, truck response time averages 11 minutes and 6 seconds. Finally, 20.7% of service incidents within the Fire Station 18 Service Area are responded to by Personnel from Fire Station 16, thus increasing the burden on facilities and personnel to the adjacent area. In order to ensure the public health and safety, the following conditions are required for this project:
The Fire Department's conditions of approval include the following:
1. Subject to exception (a) set forth below, a Certificate of Occupancy for any building within the project footprint shall not be issued until construction of Permanent Fire Station 18 has commenced. Upon commencement of construction of Permanent Fire Station 18 and subject to the exception (b) set forth below, the Director may issue Certificates of Occupancy for any building within the project footprint provided that all conditions of approval and all applicable provisions of the Fresno Municipal Code have been satisfied. Upon written request of the applicant, the Director may issue Certificates of Occupancy for up to 10% of the dwelling units in an approved subdivision map or planned development after full funding for construction is secured but prior to commencement of construction.
Exceptions to the above provision are as follows:
a. If construction of Permanent Fire Station 18 has not commenced by August 1, 2019, an applicant or developer may submit a written request to the DARM Director seeking a determination of when Certificates of Occupancy may be issued for the subject project. The Director, in consultation with the City Manager, Public Works Director, and Fire Chief shall make a determination regarding issuance of Certificates of Occupancy. This determination may result in an amendment to project conditions depending upon the nature of the project and the circumstances at the time of the request.
b. If the Director, in consultation with the City Manager, Public Works Director, and Fire Chief, determines following commencement of construction, construction of Permanent Fire Station 18 has ceased for six months or more, further Certificates of Occupancy shall not be issued until construction recommences or the cause of delay has otherwise been resolved.
2. Projects that will not have a hold on issuance of Certificates of Occupancy after payment of applicable fees and a determination by the Director that all conditions of approval and all applicable provisions of the Fresno Municipal Code have been satisfied are the following:
a. Fast food restaurants of 5,000 square feet or less with or without a drive-through.
b. Commercial uses of 10,000 square feet or less located within existing retail or commercial centers, which are intended to serve existing populations.
c. Public facilities intended to serve existing populations.
Landscaping/Walls/Open Space
The proposed subdivision is located adjacent to and abutting collector streets (North Hayes and West Gettysburg Avenues) within the boundaries of the West Area Community Plan and the development will be required to install landscaping and irrigation within a minimum 15-foot wide landscape strip along the major street frontages. A six-foot high concrete/masonry wall is required to be constructed at the rear of the landscaped areas along the major streets.
Furthermore, as referenced herein above, a trail will be developed along West Gettysburg Avenue as well as dedications for a Class 1 bicycle and pedestrian trail on Outlots "A", "B" and "C." Outlot "D" shall be dedicated for public open space and future right-of-way, and Outlot "E" shall be dedicated to provide pedestrian access from West Norwich to West Gettysburg Avenues.
The developer is required to provide street trees on all public street frontages per Fresno Municipal Code and for the dedication of planting and buffer landscaping easements as determined by the Planning Department. Street trees shall be planted at the minimum rate of one tree for each 60' of street frontage or one tree per home (whichever is greater) by the Developer. Furthermore, the developer is required to provide irrigation for all street trees. The irrigation system shall comply with FMC Section 15-2309, Irrigation Specifications and AB1881.
The long term maintenance and operating costs, including repair and replacement, of certain required public improvements ("Services") associated with all new Single-Family Developments (e.g., landscaped areas, concrete curb and gutters, sidewalks, curb ramps, median islands, etc.) are the ultimate responsibility of the Developer. The Developer shall provide for maintenance of these "Services" either by a mechanism approved by the Public Works Department or by annexing to the City of Fresno's Community Facilities District No. 11 ("CFD No. 11").
Streets and Access Points
The Fresno General Plan designates West Gettysburg and North Hayes Avenues as collector streets. The project will take access from one point along North Olinda Avenue and one point on West Gettysburg Avenue. The developer of this project will be required to dedicate and construct improvements along all major street frontages and on all interior local streets within the subdivision. Direct vehicular access will be relinquished along all major street frontages of single family residential lots. The subdivision design includes boundary streets along its western and southern boundaries in order to afford access and facilitate connectivity for future development on adjacent undeveloped property. The proposed project also provides a pedestrian connection/paseo from the interior of the subdivision to the required trail on West Gettysburg Avenue.
The proposed project is located within Traffic Impact Zone III pursuant to Figure MT-4 of the Fresno General Plan, which generally represents areas near or outside the City Limits but within the SOI as of December 31, 2012.
The analysis of traffic operations within the MEIR was conducted based on roadway segments representative of the City's overall transportation network. Traffic volumes on the selected roadway segment analysis is based on traffic counts taken at single location or link, which was intended to be representative of the entire segment. A link connects two intersections; a segment is a series of links. Traffic operations on the study roadway segments were measured using a qualitative measure called Level of Service (LOS). LOS is a general measure of traffic operating conditions whereby a letter grade, from "A" (the best) to "F" (the worst), is assigned. These grades represent the perspective of drivers and are an indication of the comfort and convenience associated with driving, as well as speed, travel time, traffic interruptions, and freedom to maneuver.
The threshold established by the Fresno General Plan in TIZ III is Level of Service "D" representing a high-density, but stable flow. Users experience severe restriction in speed and freedom to maneuver, with poor levels of comfort and convenience.
Vehicle trips projected to be generated by the proposed project were calculated using the Institute of Traffic Engineers (ITE) Trip Generation Manual, 9th Edition. Based upon the calculations, the proposed project is projected to generate 935 Average Daily Trips (ADT) with 73 vehicle trips occurring during the morning (7 to 9 a.m.) peak hour travel period and 98 vehicle trips occurring during the evening (4 to 6 p.m.) peak hour travel period. Although the project is not anticipated to generate traffic volumes exceeding 100 peak hour trips, a Traffic Impact Analysis (TIA) was prepared to assess the impacts of the new development on existing and planned streets. Furthermore, a supplemental assessment of additional intersections was also made by the traffic consultant responsible for preparation of the TIA in June of 2019. These assessments evaluated the impacts of the project by analyzing the following 11 study intersections and five study segments in the vicinity of the project during the AM and PM peak hours for the Existing Conditions; Existing plus Project Conditions; Near Term Plus Project Conditions; and, Cumulative Year 2035 plus Project Conditions study scenarios:
Study Intersections:
1. Hayes Avenue/Shaw Avenue
2. Bryan Avenue/Gettysburg Avenue
3. Hayes Avenue/Gettysburg Avenue
4. Polk Avenue/Gettysburg Avenue
5. Hayes Avenue/Ashlan Avenue
6. Polk Avenue/Ashlan Avenue
7. Polk Avenue/Shaw Avenue
8. SR 99 SB Ramps/Shaw Avenue
9. SR 99 NB Ramps/Shaw Avenue
10. SR 99 SB Off-Ramp/Ashlan Avenue
11. SR 99 NB Off-Ramp/Ashlan Avenue
Study Segments:
1. Hayes Avenue between Shaw Avenue and Gettysburg Avenue
2. Hayes Avenue between Gettysburg Avenue and Ashlan Avenue
3. Gettysburg Avenue between Bryan Avenue and Hayes Avenue
4. Gettysburg Avenue between Hayes Avenue and Polk Avenue
5. Ashlan Avenue between Hayes Avenue and Polk Avenue
Based on the analyses included in the TIA and supplemental assessment, all of the intersections are currently operating above the TIZ III LOS standard of LOS D and all of the study roadway segments are currently operating above the TIZ III LOS D Standard. The intersections of Hayes Avenue at Shaw Avenue and Polk Avenue at Ashlan Avenue currently satisfy Traffic Signal Warrant 1 - Eight Hour Vehicular Volume and Traffic Signal Warrant 2 - Four Hour Vehicular Volumes as defined in the California Manual of Uniform Traffic Control Devices (MUTCD). These findings comprise the Existing Conditions Scenario.
With the addition of the project (Existing plus Project Conditions Scenario), all intersections and roadway segments are projected to continue to operate above the TIZ III LOS D standard with the addition of the project. The intersection of Polk Avenue at Ashlan Avenue is also projected to satisfy the Traffic Signal Warrant 3 - Peak Hour during the PM peak hour with the addition of the project. The Conditions of Approval and the project specific mitigation measures for the proposed project require the installation of a traffic signal with protected left-turn phasing at the intersection of Polk and Ashlan Avenues (at ultimate location, including right-of-way acquisition as necessary), the installation of an all-way stop control at the intersection of Bryan and Gettysburg Avenues with school crosswalks and signage. Therefore, the proposed project will not result in any significant direct or primary effects or impacts.
The TIA also analyzed the operational impacts with the addition of previously approved and pending projects along with the proposed project (Near Term plus Project Conditions Scenario). This is one future assumed scenario which is utilized to consider indirect or secondary effects or impacts which are caused cumulatively by the project and other future projects at a point later in time or farther removed in the distance, but which are still reasonably foreseeable.
The analysis included in the TIA show the following locations and time period, for the Near Term plus Project Scenario, which are projected to operate below the City of Fresno TIZ III LOS D standard and/or satisfy the Traffic Signal Warrant 3 - Peak Hour:
* Near Term Plus Project
o Hayes Avenue at Shaw Avenue
* LOS F - AM and PM peak hours
* Peak Hour Warrant - AM and PM peak hours
o Polk Avenue at Gettysburg Avenue
* LOS F - AM peak hour
* Peak Hour Warrant - AM and PM peak hours
o Polk Avenue at Ashlan Avenue
* LOS F - PM peak hour
* Peak Hour Warrant - AM and PM peak hours
o Hayes Avenue at Ashlan Avenue
* Peak Hour Warrant - PM peak hour
o Polk Avenue at Shaw Avenue
* LOS F - AM and PM peak hours
The project TIA notes that between the Existing Traffic Conditions and the Near Term plus Project Traffic Conditions scenarios, the Project accounts for 1.7 percent of the daily trips, 1.7 percent of the AM peak hour trips and 1.8 percent of the PM peak hour trips of growth in traffic, while the rest can be attributable to the near term projects. Therefore, the TIA provides that the majority of the mitigation measures presented under this scenario may not be necessary immediately upon completion of the proposed Project. Regardless, all of these intersections are included within the City of Fresno impact fee programs and all study roadway segments are projected to continue to operate above the TIZ III LOS D standard with the addition of the proposed project and all approved/pending projects.
Finally, under the Cumulative Year 2035 plus Project Traffic Conditions scenario, the TIA provides that the following intersections are projected to operate below the City of Fresno TIZ III LOS D standard and/or satisfy the Traffic Signal Warrant 3 - Peak Hour:
* Cumulative Year 2035 Plus Project
o Hayes Avenue at Shaw Avenue
* LOS F - AM and PM peak hours
* Peak Hour Warrant - AM and PM peak hours
o Bryan Avenue at Gettysburg Avenue
* LOS F - AM and PM peak hours
* Peak Hour Warrant - AM and PM peak hours
o Hayes Avenue at Gettysburg Avenue
* LOS F - AM and PM peak hours
* Peak Hour Warrant - AM and PM peak hours
o Polk Avenue at Gettysburg Avenue
* LOS F - AM and PM peak hours
* Peak Hour Warrant - AM and PM peak hours
o Polk Avenue at Ashlan Avenue
* LOS F - PM peak hour
* Peak Hour Warrant - AM and PM peak hours
o Hayes Avenue at Ashlan Avenue
* Peak Hour Warrant - PM peak hour
o Polk Avenue at Shaw Avenue
* LOS F - AM and PM peak hours
o State Route (SR) 99 Southbound (SB) ramps at Shaw Avenue
* LOS F - PM peak hour
o SR 99 Northbound (NB) ramps at Shaw Avenue
* LOS F - PM peak hour
o SR 99 NB off-ramp at Ashlan Avenue
* LOS F - PM peak hour
The project TIA also calculated the Project's fair share percentage impact to study intesections projected to fall below their LOS threshold under the Cumulative Year 2035 plus Project scenario, as follows:
* Project's Fair Share (%)
o Polk Avenue at Shaw Avenue
* 1.69%
o State Route (SR) 99 Southbound (SB) ramps at Shaw Avenue
* 1.63%
o SR 99 Northbound (NB) ramps at Shaw Avenue
* 1.41%
o SR 99 NB off-ramp at Ashlan Avenue
* 0.33 %
While it is recommended that the Project contribute its equitable fair share for the future improvements necessary to maintain an acceptable LOS, fair share contributions should only be made for those facilities or portion thereof currently not funded by the responsible agency's roadway impact fee programs, as appropriate.
The City of Fresno General Plan includes multiple policies related to transportation funding and regional level coordination. These policies are crafted so that new development pays the proportional share of the developments impacts. These policies identify continued support for the implementation of metropolitan-wide and region-wide transportation impact fees to cover the proportional share of the developments impacts and need for a comprehensive multi-modal transportation system that are not funded by other sources.
The Citywide Regional Street Impact Fee Program and the New Growth Area Major Street Impact Fee Program are collectively referred to as the Fresno Major Street Impact Fee Program (FMSI Fee Program). The FMSI Fee Program was implemented to provide a funding mechanism for transportation facilities required to serve future development through 2025. The FMSI Fee Program is a successor fee program that replaced the previous transportation facility components of the City's Urban Growth Management (UGM) fee program.
The Fresno General Plan establishes growth projections through the General Plan Horizon year of 2035 as well as through build out of the General Plan. The General Plan includes goals, objectives, and implementing policies for the transportation system. A General Plan traffic model was prepared that was consistent with the goals, objectives, and policies of the General Plan. In accordance with the identified transportation needs based on traffic volume growth forecasts generated by the traffic model, the City's Public Works Department subsequently provided an FMSI Fee Program Capital Improvement Program (Street CIP) that outlines the planned facilities and costs for FMSI Fee Program funded transportation improvements through General Plan build out.
The Street CIP details the roadway improvement projects needed to accommodate future development that will be funded through the FMSI Fee Program. For each street segment, the Street CIP includes: travel lanes; medians and median landscaping; parking lanes; bike lanes; curb and gutter; bus bays; irrigation pipes and canals; railroad crossings; and, soft costs (engineering, plan check, and inspection costs). In addition to the street improvements, the Street CIP also includes associated right of way acquisition, ancillary costs (mobilization traffic control, dust control, and storm water pollution prevention), bridge widening, and other miscellaneous improvements. Asphalt concrete dikes, utilities, sidewalks, street lights, sound walls, and frontage landscaping are specifically excluded from the Street CIP. The FMSI Fee Program also will not fund construction of improvements required to cure existing street deficiencies, as measured by level of service standards.
The proposed project will pay both FMSI Program fees, including: (1) The Citywide Regional Street Impact Fee (Citywide Fee) applicable to all new residential, retail, office, and industrial development in both the Infill and New Growth areas. (this fee funds larger regional transportation improvements that are designed to accommodate traffic volumes resulting from development on a citywide basis); and, (2) The New Growth Area Major Street Impact Fee (New Growth Fee) applicable to only development in the New Growth areas of the City (this fee funds major streets that are located in the New Growth Area and primarily serve and benefit new development in the New Growth Area).
The TSMI fee facilitates project impact mitigation to the City of Fresno Traffic Signal infrastructure so that costs are applied to each new project/building based on the generated ADT. The TSMI fee is credited against traffic signal installation/modifications and/or Intelligent Transportation System (ITS) improvements (constructed at their ultimate location) that plan to build out the 2035 General Plan circulation element and are included in the Nexus Study for the TSMI fee. The TSMI fee is regularly updated as new traffic signals are added, new grant funds offset developer improvement costs, and/or construction costs increase/decrease. If the project is conditioned with traffic signal improvements in excess of their TSMI fee amount, the applicant may apply for fee credits (security/bonding and/or developer agreement required) and/or reimbursement for work in excess of their fee as long as the infrastructure is in place at the ultimate location. The applicant should work with the Public Works Department and identify, with a Professional Engineers estimate, the costs associated with the improvements prior to paying the TSMI fee to determine any applicable fee credits and/or reimbursements.
For project specific impacts that are not consistent with the 2035 General Plan, Public Works Standards, and/or are not incorporated into the TSMI fees, the infrastructure costs will not be eligible for reimbursement unless the City Engineer and City Traffic Engineer include the new traffic signal and/or ITS infrastructure in the next TSMI fee update and the applicant agrees to pay the new TSMI fee that includes the new infrastructure. Failure to pay this fee or construct improvements that are credited/reimbursable with this fee will result in a significant unmitigated impact as this fee is applied to all projects within the City Sphere of Influence.
The Regional Transportation Mitigation Fee (RTMF) is an important part of the Measure "C" Extension approved by Fresno County voters in 2006 (continuing a one-half cent sales tax for transportation purposes). The RTMF is intended to ensure that future development contributes to its fair share towards the cost of infrastructure to mitigate the cumulative, indirect regional transportation impacts of new growth in a manner consistent with the provisions of the State of California Mitigation Fee Act. The fees will help fund improvements needed to maintain the target level of service in the face of higher traffic volumes brought on by new developments. Current Measure "C" projects include but are not limited to the Veteran's Boulevard project for northwest Fresno which will include a new interchange on State Route 99 and a two and one-half mile arterial from Herndon Avenue to Grantland Avenue. The new interchange will be located on State Route (SR) 99 between the Herndon Avenue and Shaw Avenue interchanges; and, is expected to improve access to SR99, provide congestion relief to northwest Fresno, and connect northwest Fresno to the communities west of State Route 99. The RTMF is governed by a Joint Powers Agency which is the same as the Fresno Council of Governments (COG) Board. Fresno COG's primary functions are transportation planning and programming. As a state-designated Regional Transportation Planning Agency (RTPA) and federally-designated Metropolitan Planning Organization (MPO) for Fresno County, Fresno COG must comply with both designation requirements. Fresno COG prepares a Regional Transportation Plan (RTP) that looks 25 years into the future, and sets policies for a wide variety of transportation options and projects. It guides how and where people and goods will travel by identifying both existing and needed transportation facilities. Fresno COG prepares the region's Federal Transportation Improvement Program, a four-year program of financially constrained transportation projects consisting of highway, transit, bicycle, and pedestrian projects that are selected through an approved project selection process.
The project conditions of approval and mitigation measures also require payment of the Fresno Major Street Impact (FMSI) Fee, the Traffic Signal Mitigation Impact (TSMI) Fee, and the Regional Transportation Mitigation Fee (RTMF).
Improvements at the following study intersections are included in the TSMI fee program:
* Hayes Avenue at Shaw Avenue
* Bryan Avenue at Gettysburg Avenue
* Hayes Avenue at Gettysburg Avenue
* Polk Avenue at Gettysburg Avenue
* Hayes Avenue at Ashlan Avenue
* Polk Avenue at Ashlan Avenue
* Polk Avenue at Shaw Avenue
* SR 99 SB ramps at Shaw Avenue
* SR 99 NB ramps at Shaw Avenue
* SR 99 SB ramps at Ashlan Avenue
As these locations and respective improvements are presently covered by local and regional roadway impact fee programs, and, given that the Project will contribute its equitable fair share through payment into those impact fee programs, the project satisfies its traffic mitigation obligations toward cumulative impacts.
As noted within the Mitigated Negative Declaration prepared for the proposed project, the environmental assessment was tiered from the City of Fresno General Plan Master Environmental Impact Report (MEIR). Section 5.13 of the MEIR related to Transportation and Traffic describes potential impacts to the transportation system associated with adoption of the City of Fresno General Plan Update. The study area for cumulative transportation and traffic impacts included the Planning Area and the immediate surrounding County of Fresno, City of Clovis, and surrounding Counties areas because cumulative development in the areas immediately surrounding the Planning Area could combine with development under the proposed project and result in cumulative transportation and traffic impacts. Project specific impacts identified due to increases in peak hour traffic volumes were based on build out of the City of Fresno General Plan Update along with existing development in the remainder of Fresno County. Along with build out of planned population and employment, the analysis assumed the transportation system displayed in Appendix H-7 and H-8. The findings of the MEIR concluded that build out of the City of Fresno General Plan Update would add vehicle trips to roadways that would result in operations below the adopted level of service thresholds in the City, unincorporated Fresno County, City of Clovis, and to Caltrans facilities constituting a significant impact.
Build out of the City of Fresno General Plan Update would add vehicle trips to roadways that would result in operations below the City of Fresno General Plan LOS D under existing conditions. Based on the LOS identified in Exhibits 5.14-5 and 5.14-6 (See Appendix H-8 and H-9, respectively, for detail), the roadway segments of Shaw Avenue from the State Route 99 Northbound Ramps to Cornelia Ave was projected to operate at LOS E during the AM Peak hour and LOS F during the PM Peak hour; and, the segment of Shaw from Cornelia to Jennifer Avenues was projected to operate at LOS F during the PM Peak hour.
Although some study intersections have been projected to operate below the TIZ III LOS D standard under various scenarios, it must be noted that the General Plan Update allows LOS E and LOS F on the roadway segments identified in Exhibits 5.14-5 and 5.14-6 with the implementation of the General Plan Update in TIZ III. This reflects a change in policy for the City of Fresno to acknowledge that transportation planning based solely on roadway LOS, which considers only driver comfort and convenience, is not desirable since it fails to acknowledge other users of the circulation system and other community values.
In evaluating the roadway system, a lower LOS may be desired when balanced against other community values related to resource protection, social equity, economic development, and consideration of pedestrians, bicyclists, and transit users. The Fresno General Plan utilizes and encourages strategic initiatives in compliance with the California Complete Streets Act, which provides priority and emphasis on a multi-modal transportation system; more transportation options result in fewer traffic jams and the overall capacity of the transportation network increases. Therefore, providing more transportation options will allow the City to meet its future travel demands without solely relying on motorized vehicles. In addition, roadway LOS is directly linked to roadway infrastructure costs. A higher LOS results in greater expenditure of infrastructure for wider roadways that do not necessarily serve all users of the circulation system and may compete with other policies of the General Plan Update.
The City of Fresno General Plan will accommodate planned population and employment growth without expanding its current SOI, accommodating 180,000 more people than the previous General Plan in the same area. The intent is to accommodate anticipated growth though compact, walkable, infill, new complete neighborhoods, and mixed-use development through intensification of the downtown planning area, high capacity transit corridors, intensive urban activity centers, and multi-modal districts. This focus will locate population and employment closer to services. As discussed under Impact TRANS-1 in the MEIR, increased development density and intensity is correlated with reduced vehicle trips. Mixing complementary uses in a neighborhood setting increase internal trip "capture," and different urban design approaches increase transportation connectivity and provide high-quality bicycle, pedestrian, and transit facilities by increasing the relative attractiveness of non-automobile modes of travel to promote travel mode shifts. The City of Fresno General Plan Update also provides a complete streets approach, which considers all modes of transportation, in the planning, design and implementation facilities to support planned population and employment growth. Even with this focus on more compact development and complete street concepts, vehicle travel as measured in terms of Vehicle Miles Traveled (VMT) is forecast to increase.
This General Plan shifts emphasis from a city dominated by suburban growth to one that also shares increased urban development in the form of infill and rehabilitation, along with new Activity Centers with mixed-uses and neighborhoods in growth areas. The basis of this Plan's concepts are formed by balancing more efficient infill, Downtown, and neighborhood revitalization; transit-oriented development along major streets; mixed-uses in new Activity Centers in growth areas; and the building of Complete Neighborhoods.
Major urban form components include Activity Centers with mixed-uses, intensification, and infill development. Some of these Activity Centers are generally located on land along the first phase of the BRT system. The first phase is composed of BRT corridors along Blackstone Avenue between Downtown and the major shopping centers from Herndon Avenue to Nees Avenue, and along Ventura Avenue-Kings Canyon Road from Downtown to Clovis Avenue. Concurrently there will be enhanced bus service along Shaw Avenue.
As demand necessitates, later phases of BRT may include the Shaw Avenue corridor, which will support the opportunity for focused intensity at the West Shaw Activity Center proposed at Veterans Boulevard and Shaw Avenue west of State Route 99, extending south along Grantland Avenue to the Grantland Transit Village between Ashlan and Shields Avenues.
Employment centers in existing developed areas and in growth areas, composed of high concentrations of office, business parks and districts, and industrial clusters, are also important components of urban form. These areas have traditionally been served by freeways, freight rail, and major streets, and now will be additionally served by proposed BRT corridors with more intense land uses generating many new business and employment opportunities. These General Plan objectives and policies are intended to reduce regional trips and citywide congestion. The General Plan and MEIR acknowledge that even if local congestion increases due to an increase in population from infill, this will eventually improve air quality by reducing per capita vehicle emissions and VMT through shorter commutes and increase in transit and non-motorized modes of travel. This will also reduce the need for regional travel demand transportation improvements.
Therefore, with implementation of the General Plan, impacts to roadways within TIZ III were concluded to be less than significant by the MEIR based upon a cumulative year 2035 study scenario.
While implementation of the policies included in the City of Fresno General Plan are recognized in the MEIR as adequate to ensure funding for new development's impacts to transportation facilities that would contribute to planned expansion of the transportation system, it must be acknowledged that improvements to the freeway system are for roadways under Caltrans' jurisdiction. Therefore, the City of Fresno does not have control over their timing or implementation, and the respective impacts identified within the MEIR were identified as remaining significant and unavoidable.
In 2014, through passage of Council Resolution No. 2014-225, the City of Fresno adopted Findings of Fact related to Significant and Unavoidable Effects as well as Statements of Overriding Considerations including but limited to the those streets with an acceptable LOS E or F standard in order to certify Master Environmental Impact Report SCH No. 2012111015 for purposes of adoption of the Fresno General Plan. Section 15093 of the California Environmental Quality Act requires the lead agency to balance the benefits of a proposed project against its unavoidable environmental risks in determining whether to approve the project.
In keeping with the strategic initiatives and with consideration to balancing the roadway system against other community values, the adopted Statements of Overriding Considerations for the MEIR addressed Findings of Significant Unavoidable Impacts within the categories/areas of Transportation and Traffic; citing specific economic, legal, social, technological, or other considerations, including provision of employment opportunities for highly trained workers as project goals, each and all of which were deemed and considered by the Fresno City Council to be benefits, which outweighed the unavoidable adverse environmental effects attributed to development occurring within the City of Fresno Sphere of Influence (SOI), consistent with the land uses, densities, and intensities set forth in the Fresno General Plan.
The Public Works Department, Traffic Engineering Division has reviewed the potential traffic related impacts for the proposed project and has determined that the streets adjacent to and near the subject site will be able to accommodate the quantity and kind of traffic which may be potentially generated subject to the requirements outlined within the memoranda from the Traffic Engineering Division dated March 11, 2019. These requirements generally include: (1) The provision of a minimum two points of vehicular access to major streets for any phase of the development; (2) Major and local street dedications; (3) Dedications of bicycle, pedestrian and landscape easements for trail purposes; (4) Street improvements, (including, but not limited to, construction of concrete curbs, gutters, pavement, underground street lighting systems; and, (5) Payment of applicable impact fees (including, but not limited to, the Traffic Signal Mitigation Impact (TSMI) Fee, and the Fresno Major Street Impact (FMSI) Fee.
The project has also been conditioned to comply with mitigation measure requirements of the Traffic Engineer Manager outlined in the memoranda dated July 19, 2018, for review of the traffic impact analysis for TIS 18-007. Mitigation measures, in addition to payment of required fees, include the installation of a traffic signal at the intersection of Polk and Ashlan Avenues, and an all-way stop control at the intersection of Bryan and Gettysburg Avenues.
Therefore, the Public Works Department/Traffic Engineering Division has determined that, based upon the proposed traffic yield from and the expected traffic generation of the proposed project for the subject property, the proposed project will not adversely impact the existing and projected circulation system based upon implementation of the mitigation measures included within the MEIR and based upon compliance with the project specific mitigation measures referenced herein.
Council District Plan Implementation Committee
The Council District 1 Project Review Committee did not review the project.
Notice of Planning Commission Hearing
The Development and Resource Management Department mailed notices of this Planning Commission hearing to surrounding property owners within 1,000 feet of the subject property (see attached Noticing Vicinity Map - Exhibit G).
Public Response
At the time of publication, two appeal letters had been received by the Development and Resource Management Department (see attached Appeal Letters - Exhibit K). These letters identify several issues which the appellants believe were not adequately addressed in the project Conditions of Approval and Mitigated Negative Declaration, primarily regarding traffic, tract design/layout, air and water quality, and fire department service.
LAND USE PLANS AND POLICIES
As proposed, the project will be consistent with the Fresno General Plan goals and objectives related to residential land use and the urban form:
* Provide for a diversity of districts, neighborhoods, housing types (including affordable housing), residential densities, job opportunities, recreation, open space, and educational venues that appeal to a broad range of people throughout the city.
* Plan for a diverse housing stock that will support balanced urban growth, and make efficient use of resources and public facilities.
* Make full use of existing infrastructure, and investment in improvements to increase competitiveness and promote economic growth.
* Promote orderly land use development in pace with public facilities and services needed to serve development.
* Encourage the development of Complete Neighborhoods and districts with an efficient and diverse mix of residential densities, building types, and affordability which are designed to be healthy, attractive, and centered by schools, parks, and public and commercial services to provide a sense of place and that provide as many services as possible within walking distance. Healthy communities demonstrate efficient development patterns providing for: Sufficient affordable housing development in appropriate locations; A mix of land uses and a built environment that supports walking and biking; Multimodal, affordable transportation choices; and, Safe public spaces for social interaction.
These Goals contribute to the establishment of a comprehensive city-wide land use planning strategy to meet economic development objectives, achieve efficient and equitable use of resources and infrastructure, and create an attractive living environment in accordance with Objective LU-1 of the Fresno General Plan.
Policy UF-1-d further emphasizes provisions for a diversity and variation of building types, densities, and scale of development in order to reinforce the identity of individual neighborhoods, foster a variety of market-based options for living and working to suit a large range of income levels, and further affordable housing opportunities throughout the city.
Likewise, Objective LU-5 of the General Plan calls for a diverse housing stock that will support balanced urban growth, and make efficient use of resources and public facilities; and, Implementing Policy LU-5-c promotes medium density residential use to maximize efficient use of residential property through a wide range of densities.
Objective UF-12 of the Fresno General Plan directs the City to locate roughly one-half of future residential development in infill areas - defined as being within the City on December 31, 2012 - including the Downtown core area and surrounding neighborhoods, mixed-use centers and transit-oriented development along major BRT corridors, and other non-corridor infill areas, and vacant land.
Supporting Policy LU-1-a of the Fresno General Plan also promotes new development within the existing City limits as of December 31, 2012. Policies LU-1-e and LU-1-g recommend that annexations to the City conform to the General Plan Land Use Designations and maintain the City's current Sphere of Influence (SOI) Boundaries without additional expansion.
The subject property (approximately 17.45 acres) qualifies as infill development under the definition provided in the Fresno General Plan as the subject property was annexed with Annexation No. 1298 on April 13, 2006. Evaluation of public services capacity and availability for the area has determined that public infrastructure improvements exist within the area to serve existing development within the vicinity as well as future development on the subject property. Water mains and sewer mains have been developed in the subject quarter section to provide service for the proposed development. Furthermore, the proposed project will be obligated to pay fair share and proportional payment of fees and all development mitigation costs.
The goals of the West Area Community Plan include developing the West Area as a planned community with a complete range of services and facilities for the needs of the community residents, in adherence to a set of specific standards for residential, commercial, industrial, and public infrastructure development, with special emphasis on minimization of land use conflict between agriculture and urban uses.
Objective W-1 of the West Area Community Plan supports this goal by promoting compatibility between areas planned for, or committed to, active farming operations and areas planned for urban development.
Objective W-3 of the West Area Community Plan encourages providing streetscapes which create a positive image of the West Area and contribute to the West Area Community's quality of life.
Objective W-4 of the West Area Community Plan also encourages the establishment and maintenance of safe, attractive, and stable residential neighborhoods; to preserve the long-term integrity of the community.
This project supports the above mentioned policies in that the density and intensity of the proposed development conform to the applicable Medium Density Residential land use designation of the Fresno General Plan and West Area Community Plan.
The proposed development of the subject property will contribute to the completion of missing roadway and infrastructure improvements within the area in a manner which is consistent with the land use designations and circulation element of the Fresno General Plan. The proposed project will also provide for connectivity through both vehicular and pedestrian integration with adjacent land for future development.
The project is located to the east of the Central Unified School District Harvest Elementary and Glacier Point Middle Schools and is approximately half a mile west of Teague Elementary School.
Therefore it is staff's opinion that the proposed project is consistent with respective general and community plan objectives and policies and will not conflict with any applicable land use plan, policy or regulation of the City of Fresno. Furthermore, the proposed project, including the design and improvement of the subject property, is found; (1) To be consistent with the goals, objectives and policies of the applicable Fresno General Plan and West Area Community Plan; (2) To be Suitable for the type and density of development; (3) To be safe from potential cause or introduction of serious public health problems; and, (4) To not conflict with any public interests in the subject property or adjacent lands.
ENVIRONMENTAL FINDING
An environmental assessment initial study was prepared for this project in accordance with the requirements of the California Environmental Quality Act (CEQA) Guidelines. This process included the distribution of requests for comment from other responsible or affected agencies and interested organizations.
Preparation of the environmental assessment necessitated a thorough review of the proposed project and relevant environmental issues and considered previously prepared environmental and technical studies including the Fresno General Plan Master Environmental Impact Report (MEIR SCH No. 2012111015). These environmental and technical studies have examined projected sewage generation rates of planned urban uses, the capacity of existing sanitary sewer collection and treatment facilities, and optimum alternatives for increasing capacities; groundwater aquifer resource conditions; water supply production and distribution system capacities; traffic carrying capacity of the planned major street system; and, student generation projections and school facility site location identification.
The proposed project has been determined to be a subsequent project that is not fully within the scope of the MEIR SCH No. 2012111015 as provided by the CEQA, as codified in the Public Resources Code (PRC) Section 21157.1(d) and the CEQA Guidelines Section 15177(c). Therefore, the Development and Resource Management Department proposes to adopt a Mitigated Negative Declaration for the proposed project, which is tiered off the Fresno General Plan Master Environmental Impact Report (MEIR No. 2012111015)
It has been further determined that all applicable mitigation measures of SCH No. 2012111015 have been applied to the project, together with project specific mitigation measures, as necessary to assure that the project will not cause significant adverse cumulative impacts, growth inducing impacts and irreversible significant effects beyond those identified by SCH No. 2012111015 as provided by CEQA Section 15178(a). In addition, pursuant to Public Resources Code, Section 21157.6(b)(1), staff has determined that no substantial changes have occurred with respect to the circumstances under which the MEIR was certified and that no new information, which was not known and could not have been known at the time that the MEIR was certified as complete, has become available. Therefore, it has been determined based upon the evidence in the record that the project will not have a significant impact on the environment and that the filing of a mitigated negative declaration is appropriate in accordance with the provisions of CEQA Section 21157.5(a)(2) and CEQA Guidelines Section 15178(b)(1) and (2).
Based upon the attached environmental assessment and applicable mitigation measures, staff has determined that there is no evidence in the record that the project may have a significant effect on the environment and has prepared a Mitigated Negative Declaration for this project. A public notice of the attached Mitigated Negative Declaration for Environmental Assessment Application No. T-6215/UGM was published on May 10, 2019; there have been no comments received to date.
FRESNO MUNICIPAL CODE FINDINGS
Based upon analysis of the applications, staff concludes that the required findings contained within FMC Section 15-3309 (Vesting Tentative Tract Map Findings) of the Fresno Municipal Code can be made. These findings are attached as Exhibit F.
GROUNDS FOR DENIAL OF TENTATIVE MAP
The Subdivision Map Act (California Government Code �� 66410, et seq.) provides that approval of a proposed subdivision map shall be denied if any of the following findings are made.
1. That the proposed map is not consistent with applicable general and specific plans as specified in Section 65451 of the SMA.
2. That the design or improvement of the proposed subdivision is not consistent with applicable general and specific plans.
3. That the site is not physically suitable for the type of development.
4. That the site is not physically suitable for the proposed density of development.
5. That the design of the subdivision or the proposed improvements are likely to cause substantial environmental damage or substantially and avoidably injure fish or wildlife or their habitat.
6. That the design of the subdivision or type of improvements is likely to cause serious public health problems.
7. That the design of the subdivision or the type of improvements will conflict with easements, acquired by the public at large, for access through or use of, property within the proposed subdivision. In this connection, the governing body may approve a map if it finds that alternate easements, for access of or use, will be provided, and that these will be substantially equivalent to ones previously acquired by the public. This subsection shall apply only to easements of record or to easements established by judgment of a court of competent jurisdiction and no authority is hereby granted to a legislative body to determine that the public at large has acquired easements for access through or use of property within the proposed subdivision.
Staff has reviewed the proposed vesting tentative tract map and has determined that none of the findings above apply to the project and, therefore, has recommended approval subject to the conditions of approval.
CONCLUSION / RECOMMENDATION
The appropriateness of the proposed project has been examined with respect to its consistency with goals and policies of the Fresno General Plan and the West Area Community Plan; its compatibility with surrounding existing or proposed uses; and its avoidance or mitigation of potentially significant adverse environmental impacts. These factors have been evaluated as described above and by the accompanying environmental assessment. Upon consideration of this evaluation, it can be concluded that Vesting Tentative Tract Map No. 6215/UGM is appropriate for the project site. Planning Commission action of the proposed Vesting Tentative Tract Map, unless appealed to the Council, is final.
Attachments:
Exhibit A: Vesting Tentative Tract Map No. 6215/UGM dated
Exhibit B: Operational Statement
Exhibit C: 2019 Aerial Photograph of Site
Exhibit D: Vicinity Map
Exhibit E: Fresno General Plan Planned Land Use Map
Exhibit F: Fresno Municipal Code Findings
Exhibit G: Noticing Vicinity Map (1000 feet)
Exhibit H: Conditions of Approval for Vesting Tentative Tract Map No. 6215/UGM dated
June 19, 2019
Exhibit I: Comments and Requirements from Responsible Agencies
Exhibit J: Environmental Assessment No. T-6215/UGM, Mitigated Negative Declaration, dated May 10, 2019
Exhibit K: Appeal Letters
Historial
| Fecha | Órgano | Acción | Resultado |
|---|---|---|---|
| Wed, Jun 19, 2019 | Planning Commission | APPROVED | Pass |
Documentos adjuntos
- Exhibit A - T-6215.pdfscanned_image
- Exhibit B: Operational Statementscanned_image
- Exhibit C: Aerial Photographtagged
- Exhibit D: Vicinity Maptagged
- Exhibit E: Planned Land Usetagged
- Exhibit F: FMC Findingstagged
- Exhibit G: Noticing Mapuntagged
- Exhibit H: Conditions of Approvaltagged
- Exhibit I: Comments from Responsible Agencies - Finaltagged
- Exhibit J: Environmental Assessment No. T-6215untagged
- Exhibit K: Appeal Lettersscanned_image