RESOLUTION - Tso cai rau Tus Thawj Saib Xyuas Kev Lag Luam lossis lwm tus neeg sawv cev tso cai rau: ua txhua yam ntaub ntawv cuam tshuam rau kev thov ua ntej thiab thov rau Tsoom Fwv Teb Chaws Kev Tswj Xyuas Kev Lag Luam (FAA) rau Tshav Dav Hlau Improvement Program (AIP) cov nyiaj pab rau tsoom fwv xyoo 2015 thiab 2016 rau ob qho tib si Fresno Yosemite International Tshav Dav Hlau (Fresno Yosemite International Airports (FAT) thiab FAT) Lub nroog lub xyoo nyiaj txiag (FY) 2015 kev npaj peev nyiaj txiag txhim kho; lees txais FAA AIP cov nyiaj pab rau FY 2015 thiab FY 2016 cov haujlwm ntawm ob lub tshav dav hlau suav nrog tag nrho cov kev hloov kho tom ntej uas muaj los ntawm FAA; thiab thov rau thiab txais cov nyiaj pab thiab tag nrho cov kev hloov kho tom qab ntawd muab los ntawm California Department of Transportation Aeronautics Division rau kev sib piv cov nyiaj rau FY 2015 thiab 2016 FAA-pom zoo tej yaam num ntawm Fresno Chandler Executive Tshav Dav Hlau
Tsis siv neeg txhais lus. Qee cov ntsiab lus tseem tsis tau muaj nyob hauv hom lus no.
- Taw qhia los ntawm
- City Council
- Hnub tim
- Thu, Oct 23, 2014
- Kev tshwm sim
- Thu, Oct 23, 2014
- #
- RESO 2014-170
Full textv1
REPORT TO THE CITY COUNCIL
October 23, 2014
FROM: KEVIN R. MEIKLE, Director of Aviation
Airports Department
SUBJECT
..Title
RESOLUTION - Authorizing the Director of Aviation or other authorized representative to: execute all implicated documentation for pre-application and application to the Federal Aviation Administration (FAA) for Airport Improvement Program (AIP) grants for federal fiscal years 2015 and 2016 for both Fresno Yosemite International Airport (FAT) and Fresno Chandler Executive Airport (FCH) as shown in the City's fiscal year (FY) 2015 budget capital improvement plan; accept FAA AIP grant(s) for FY 2015 and FY 2016 projects at both airports including all subsequent amendments thereto offered by the FAA; and apply for and accept grants and all subsequent amendments thereto offered by the California Department of Transportation Aeronautics Division for matching funds for FY 2015 and 2016 FAA-approved projects at the Fresno Chandler Executive Airport
..Body
RECOMMENDATION
Approve the attached biennial Resolution authorizing the Director of Aviation or other authorized representative to execute all implicated documentation for grants and amendments thereto for both Fresno Airports, from either the FAA or the California Division of Aeronautics, for FY2015 and FY2016 projects in the City's approved FY2015 budget.
EXECUTIVE SUMMARY
The requested Resolution will allow pre-application, application, acceptance of grants and amendments, and execution of all related documents by the Director of Aviation or other authorized representative of the City for grants which may be offered by the FAA and the California Department of Transportation Division of Aeronautics (State) to both Fresno airports. The FAA is expected to offer 90% funding for Federal Fiscal Years (FFY) 2015 and 2016. The State offers grants only to FCH, which are 5% of the federal funding amount of eligible project cost. The approved Resolution must be submitted each year with the application documents. The projects identified for this next two year cycle support the Department's ongoing obligation to keep both airports safe and viable, and will generate an estimated 512 construction-related jobs.
The following required actions are permitted by the Resolution: (i) submit to the FAA and the State a required five-year Airport Capital Improvement Plan (ACIP), FAA grant Pre-Applications, and Applications for FFY 2015 and 2016 grants for both airports, (ii) accept FFY 2015 and FFY 2016 FAA grants and amendments for improvements at both airports, and (iii) apply for and accept grants and amendments as may be offered from the State (used for matching funds on FFY 2015 and FFY 2016 approved projects at FCH only).
BACKGROUND
Each FFY, the Department receives entitlement and discretionary grants from the FAA for a portion of eligible capital project costs at both Fresno airports based upon: (i) the number of passengers enplaned at FAT, (ii) the pounds of air cargo transported to FAT, (iii) the status of FCH as a "reliever" airport, and (iv) the priority of eligible projects within the FAA Western Pacific Region. The FAA is expected to offer 90 percent (90%) funding for FFY 2015 and 2016. Additional FAA discretionary grants may be received based upon applications made, federal priorities within the five-year ACIP, and the availability of funding. The Department will provide the required matching funds from local Measure C revenues (as they are received during the year) and Airport revenues. For FCH, additional matching funds may come from the State (5 percent of eligible federal funded project cost).
The five-year ACIP is the FAA's planning document to program future AIP grant funding, and is re-submitted each year for the next five years; thus refining the five-year look ahead each year. Securing FAA AIP grants includes a year-in-advance application process for projects included in the five-year ACIP, which is the reason this Resolution permitting grant related activities must be available in advance. FFY 2015 and FFY 2016 grant processing will occur under this new Resolution. FFY 2014 grant processing was accomplished using the previous Resolution 2012-147, valid for FFY 2013 and 2014. The attached updated biennial Airports Grants Resolution gives the Director of Aviation or another authorized representative the authority to comply with the FAA required application processes for FFY 2015 and 2016, the five-year FAA planning process (ACIP submittal), and the grant acceptance process for FFY 2015 and 2016 grants that may be offered to both airports. The same authorities are given for the State grants to the FCH airport. The attached Resolution has been approved as to form by the City Attorney's Office. All required local match funding will be provided from Local Measure C revenues (as they are received during the year) and Airport revenues.
The projects associated with this Resolution have been identified in the City's approved FY 2015 budget and are comprised of the following:
Fiscal Year 2015
Federal Share
FCH Demo/Clear 1333 W Whitesbridge Property
$54,000
FYI Rehabilitate Taxiway C - Design
$990,000
FYI Commercial West Ramp -- Construction
$4,500,000
FCH Update Airport Land Use Plans
$54,000
FCH Rehabilitate Taxilane - Construction Phase 1
$225,000
Fiscal Year 2016
Federal Share
FYI Part 150 Noise Mitigation Program
$1,000,000
FYI Rehabilitate Taxiway C -- Construction
$10,710,000
FYI Rehabilitate Twy B3 / B4 / C4 / B7 -- Design
$450,000
FCH Rehabilitate Taxilane - Construction Phase 2
$180,000
ENVIRONMENTAL FINDINGS
This is not a "project" for the purposes of CEQA pursuant to CEQA Guidelines, Section 15378.
LOCAL PREFERENCE
Local preference was not considered because the Resolution does not include a bid or award of a construction or services contract.
FISCAL IMPACT
There is no impact to the General Fund from this action. Approval of the Resolution will allow the Department to continue applying for and accepting grants from both the FAA and the California Division of Aeronautics for projects listed in the City's approved FY2015 Budget, and using matching funding provided by local Measure C and Airport Revenues.
Attachment: Resolution - Airports Grants FFY2015 and FFY 2016
Txhawb nqa
- Airports Department
Keeb kwm
| Hnub tim | Lub cev | Kev ua | Kev tshwm sim |
|---|---|---|---|
| Thu, Oct 23, 2014 | City Council | ADOPTED | Pass |
Cov ntawv txuas
- 10.23.14_Grants Resolutionscanned_image