Cov kev ua cuam tshuam txog Olive Gardens thiab Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline, Bid File No. 3337 (Council Districts 2, 3, 5 and County) 1. Txais qhov kev pom ntawm Categorical Exemption rau ib tus neeg ua haujlwm txiav txim siab, raws li Chav Kawm 1 Tshooj 15301(b) (Cov Tsev Kawm Ntawv uas twb muaj lawm) thiab Chav Kawm 3 Tshooj 15303(d) (Kev Tsim Kho Tshiab) ntawm CEQA Cov Lus Qhia, rau Olive Gardens thiab Van Ness Extension Water Main Replacements thiab Transfers PS201 thiab PS3 2. Muab daim ntawv cog lus tsim kho rau West Valley Construction Co. Inc., yog tus nqi ntawm $ 1,545,383 rau kev tsim kho ntawm Olive Gardens thiab Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline
Tsis siv neeg txhais lus. Qee cov ntsiab lus tseem tsis tau muaj nyob hauv hom lus no.
- Taw qhia los ntawm
- City Council
- Hnub tim
- Thu, Jun 18, 2015
- Kev tshwm sim
- Thu, Jun 18, 2015
Full textv1
REPORT TO THE CITY COUNCIL
June 18, 2015
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
THROUGH: ROBERT N. ANDERSEN, PE, Assistant Director
Public Works Department, Capital Management Division
RANDY BELL, PE, Capital Projects Manager
Public Works Department, Capital Management Division
BY: JIM POLSGROVE, Supervising Engineering Technician
Public Works Department, Capital Management Division
SUBJECT
..Title
Actions pertaining to Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline, Bid File No. 3337 (Council Districts 2, 3, 5 and County)
1. Adopt a finding of Categorical Exemption per staff determination, pursuant to Class 1 Section 15301(b) (Existing Facilities) and Class 3 Section 15303(d) (New Construction) of the CEQA Guidelines, for Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and PS201 to PS36 Raw Water Pipeline
2. Award a construction contract to West Valley Construction Co. Inc., in the amount of $1,545,383 for the construction of Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline
..Body
RECOMMENDATION
Staff recommends that the City Council adopt a finding of Categorical Exemption per staff determination, pursuant to Class 1 Section 15301(b) and Class 3 Section 15303(d) of the CEQA Guidelines and award a construction contract to West Valley Construction Co. Inc. for Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline and authorize the Public Works Director or designee to sign and execute the standardized contract on behalf of the City.
EXECUTIVE SUMMARY
The City of Fresno seeks to replace water distribution mains and water services in the Olive Gardens and Van Ness Extension areas, as well as relocating and reconnecting onsite water services. The City of Fresno will also install a new raw water transmission main between Pump Station 201 to Pump Station 36 to facilitate water treatment. Each of these areas are indicated on the attached vicinity map.
Staff recommends Council approve award of a construction contract to West Valley Construction Co. Inc. in the amount of $1,545,383 as the lowest responsive and responsible bidder for the Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline.
BACKGROUND
The project scope for Olive Gardens and Van Ness Extension Water Main Replacements and Transfers will replace water distribution mains and water services in the Olive Gardens and Van Ness Extension areas, as well as relocating and reconnecting onsite water services. The project scope for the Pump Station 201 to Pump Station 36 Raw Water Pipeline includes installation of a new raw water transmission main between Pump Station 201 to Pump Station 36 to facilitate water treatment.
Construction documents and specifications were prepared and a Notice Inviting Bids was published in the Business Journal on May 4, 2015, and posted on the City's website. Advertising efforts resulted in the participation of five (5) prospective bidders. Ultimately, four (4) sealed bid proposals were received and opened in a public bid opening on May 27, 2015, with the bids ranging from $1,545,383 to $2,187,151. West Valley Construction Co. Inc. submitted the lowest bid in the amount of $1,545,383 and is considered the lowest responsive and responsible bidder. The bid results were posted on June 2, 2015, on the City of Fresno Purchasing Division web page.
Staff recommends award of a construction contract to West Valley Construction Co. Inc. in the amount of $1,545,383 for the Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline and to authorize the Public Works Director or designee to sign and execute the standardized contract on behalf of the City.
ENVIRONMENTAL FINDINGS
Staff has performed a preliminary environmental assessment of this project and has determined that it falls within the Class 1 and 3 Categorical Exemptions set forth in Section 15301(b) and Section 15303(d) of the CEQA Guidelines which exempts existing facilities of both investor and publicly owned utilities used to provide public utility services in the Olive Gardens and Van Ness Extension areas and the new raw water transmission main between Pump Station 201 to Pump Station 36 to facilitate water treatment new raw water transmission main. Furthermore, Staff has determined that none of the exceptions to Categorical Exemptions set forth in the CEQA Guidelines, Section 15300.2 apply to this project. Staff recommends that the Council, based on its own independent judgment, adopt a finding of Categorical Exemption per staff determination, pursuant to Class 1 and 3 Categorical Exemptions set forth in Section 15301(b) and Section 15303(d) of the CEQA Guidelines for the Olive Gardens and Van Ness Extension Water Main Replacements and Transfers and Pump Station 201 to Pump Station 36 Raw Water Pipeline.
LOCAL PREFERENCE
The local preference was not implemented because the local bidder exceeded the allowable preference of $25,000.
FISCAL IMPACT
The overall cost of the project is $2,017,441 and is funded by the Water Division's FY 15 Capital Improvement Project Budget for Water Main Replacement. The project will not have any impact to the General Fund. Of the overall budget, $1,545,383 will be used for the construction contract award.
Attachments: Vicinity Map
Categorical Exemption Determination
Evaluation of Bid Proposals
Fiscal Impact Statement
Txhawb nqa
- Public Works Department
Keeb kwm
| Hnub tim | Lub cev | Kev ua | Kev tshwm sim |
|---|---|---|---|
| Thu, Jun 18, 2015 | City Council | APPROVED | Pass |