Kev nqis tes ua ntsig txog Fulton Street Reconstruction Project kev cog lus nrog American Paving Company ntawm Fresno, California 1. Pom zoo Daim Ntawv Pom Zoo Kev Sib Tham thiab Kev Sib Koom Tes, nyob rau hauv tus nqi ntawm $ 321,335, nrog American Paving Company, Royston, Hanamoto, Alley & Abey thiab Provost & Pritchard Engineering Group, Inc. 2. Pom zoo Daim Ntawv Cog Lus Hloov Daim Ntawv Cog Lus No. 74, uas ua kom cov nyiaj cog lus tsim kho ntxiv los ntawm $208,867.75 nrog American Paving Company ntawm Fresno, California

ID 21-383 · Action Item · Agenda Ready

Tsis siv neeg txhais lus. Qee cov ntsiab lus tseem tsis tau muaj nyob hauv hom lus no.

Taw qhia los ntawm
City of Fresno Capital Projects Oversight Board
Hnub tim
Mon, Mar 15, 2021

Full textv1

REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD DATE: March 15, 2021 FROM: SCOTT L. MOZIER, PE, Director Public Works Department BY: RANDALL W. MORRISON, PE, Assistant Director Public Works Department SUBJECT ..Title Actions pertaining to the Fulton Street Reconstruction Project construction contract with American Paving Company of Fresno, California 1. Approve Settlement Agreement and Mutual Release, in the amount of $321,335, with American Paving Company, Royston, Hanamoto, Alley & Abey and Provost & Pritchard Engineering Group, Inc. 2. Approve Contract Change Order No. 74, which increases the construction contract amount by $208,867.75 with American Paving Company of Fresno, California ..Body Attachments: Settlement Agreement and Mutual Release Contract Change Order No. 74

Txhawb nqa

Keeb kwm

Cov ntawv txuas