REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: August 28, 2017
FROM: THOMAS ESQUEDA, Director
Public Utility Department
BY: MICHAEL CARBAJAL, Planning Manager
Public Utilities Department
SUBJECT
..Title
Approve Friant Kern Canal Pipeline (FKCP) Project - Change Order No. 4
..Body
RECOMMENDATION
EXECUTIVE SUMMARY
BACKGROUND
ENVIRONMENTAL FINDINGS
LOCAL PREFERENCE
FISCAL IMPACT
Attachment: Change Order No. 4
Keeb kwm
| Hnub tim | Lub cev | Kev ua | Kev tshwm sim |
|---|---|---|---|
| Mon, Aug 28, 2017 | City of Fresno Capital Projects Oversight Board | APPROVED | Pass |
Cov ntawv txuas
- FKCP CCO4.pdfuntagged