Pom zoo ib qho kev hloov kho rau daim ntawv cog lus nrog NBS, tus kws pab tswv yim nyiaj txiag hauv nroog uas tshwj xeeb hauv Kev Tshawb Fawb Tus Nqi, kom tso cai rau ncua sij hawm los ua kom tiav qhov kev hloov tshiab ntawm Kev Tshawb Fawb thiab Kev Tswj Xyuas Kev Tshawb Fawb (DARM) Fee Study Analysis.
Tsis siv neeg txhais lus. Qee cov ntsiab lus tseem tsis tau muaj nyob hauv hom lus no.
- Taw qhia los ntawm
- City Council
- Hnub tim
- Thu, Aug 30, 2018
- Kev tshwm sim
- Thu, Aug 30, 2018
Full textv1
REPORT TO THE CITY COUNCIL
August 30, 2018
FROM: JENNIFER K. CLARK, Director
Development and Resource Management Department
BY: MIKE SANCHEZ, Assistant Director
Development and Resource Management Department
SUBJECT
..Title
Approve an amendment to the contract with NBS, a municipal financial consultant that specializes in Fee Studies, to allow for an extension of time to complete an update of the Development and Resource Management Department (DARM) Fee Study Analysis.
..Body
RECOMMENDATION
Staff recommends approving the amendment to the contract with NBS to June 28, 2019.
EXECUTIVE SUMMARY
NBS contracted with the City on March 26, 2018 to provide municipal fee study analysis services for the Current Planning and Building and Safety Divisions of DARM. Due to the complexities of the analysis involved, additional analysis is being requested to complete the fee study update.
BACKGROUND
On March 26, 2018, DARM entered into a contract with NBS, a financial consulting firm that specializes in user fee studies and analysis. The original term of the contract expired on August 1, 2018. Although the initial time frame was ambitious, the general complexities of such a study have caused the initial time frame to lapse.
It is being recommended that the extension of time be extended to June 28, 2019. This will allow ample to review the proposed updated fee study and conduct stakeholder meetings with those impacted by the study.
This extension does not include an increase in funding. The cost for the study has be set not to exceed $50,000.
ENVIRONMENTAL FINDING
By the definition provided in the California Environmental Quality Act (CEQA) Guidelines Section 15378 the amendment of an agreement does not qualify as a project for the purposes of CEQA.
LOCAL PREFERENCE
Local preference was not considered because this item is an amendment to an existing contract.
FISCAL IMPACT
No additional General Fund appropriations are required for this contract.
Attachments:
Exhibit A: First Amendment to Agreement
Exhibit B: Original NBS Contract
Txhawb nqa
- Planning and Development Department
Keeb kwm
| Hnub tim | Lub cev | Kev ua | Kev tshwm sim |
|---|---|---|---|
| Thu, Aug 30, 2018 | City Council | APPROVED | Pass |
Cov ntawv txuas
- Exhibit A: First Amendment to Agreementscanned_image
- Exhibit B: Original NBS Contractscanned_image