REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: August 5, 2019
FROM: DEJAN PAVIC, Public Utilities Manager
Public Utilities Department
SUBJECT
..Title
Approve Recycled Water Transmission Main Segment SW1B
(RWTM-SW1B) Project - Change Order No. 2
..Body
RECOMMENDATION
EXECUTIVE SUMMARY
BACKGROUND
ENVIRONMENTAL FINDINGS
LOCAL PREFERENCE
FISCAL IMPACT
Attachment: Change Order No. 2
Txhawb nqa
- Department of Public Utilities
Keeb kwm
| Hnub tim | Lub cev | Kev ua | Kev tshwm sim |
|---|---|---|---|
| Mon, Aug 5, 2019 | City of Fresno Capital Projects Oversight Board | APPROVED | Pass |
Cov ntawv txuas
- Garney SW1B CCO 2.pdfscanned_image