Kev nqis tes ua ntsig txog Fulton Street Reconstruction Project kev cog lus nrog American Paving Company ntawm Fresno, California 1. Pom zoo Daim Ntawv Cog Lus Hloov Daim Ntawv Cog Lus No 72, uas txo cov nqi cog lus los ntawm $283,408.21 2. Pom zoo Daim Ntawv Cog Lus Hloov Daim Ntawv Cog Lus No. 73, uas ua kom cov nyiaj cog lus nce ntxiv $360,000.00

ID19-1424 · Action Item · Agenda Ready

Tsis siv neeg txhais lus. Qee cov ntsiab lus tseem tsis tau muaj nyob hauv hom lus no.

Taw qhia los ntawm
City of Fresno Capital Projects Oversight Board
Hnub tim
Wed, Mar 20, 2019
Kev tshwm sim
Wed, Mar 20, 2019

Full textv1

REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD March 18, 2019 FROM: SCOTT L. MOZIER, PE, Director Public Works Department BY: RANDALL W. MORRISON, PE, Assistant Director Public Works Department SUBJECT ..Title Actions pertaining to the Fulton Street Reconstruction Project construction contract with American Paving Company of Fresno, California 1. Approve Contract Change Order No. 72, which decreases the contract amount by $283,408.21 2. Approve Contract Change Order No. 73, which increases the contract amount by $360,000.00 ..Body Attachments: Fulton Street - Contract Change Order No. 72 Fulton Street - Contract Change Order No. 73

Txhawb nqa

Keeb kwm

Hnub timLub cevKev uaKev tshwm sim
Wed, Mar 20, 2019City of Fresno Capital Projects Oversight BoardAPPROVED AS AMENDED