REPORT TO THE CITY COUNCIL
January 28, 2021
FROM: MICHAEL CARBAJAL, Director
Department of Public Utilities
THROUGH: BROCK D. BUCHE, PE, PLS, Assistant Director - UP&E
Department of Public Utilities - Utilities Planning & Engineering
BY: PATRICIA DIEP, Supervising Engineering Technician
Department of Public Utilities - Utilities Planning & Engineering
SUBJECT
..Title
Award a Consultant Services Agreement to Blair, Church & Flynn Consulting Engineers in an amount not to exceed $145,158 inclusive of a $10,000 contingency for the design of sewer rehabilitation improvements in the area bound by Blackstone, Maroa, McKinley, and Clinton Avenues (Council Districts 1 and 7)
..Body
RECOMMENDATIONS
Staff recommends that City Council award a Consultant Services Agreement to Blair, Church & Flynn Consulting Engineers, in the amount not to exceed $145,158 inclusive of a $10,000 contingency for the design of sewer rehabilitation improvements in the area bound by Blackstone, Maroa, McKinley, and Clinton Avenues (Project); and authorize the Director of Public Utilities, or designee, to sign and execute all documents on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Department of Public Utilities, Wastewater Management Division, is seeking to award a Consultant Services Agreement to Blair, Church & Flynn Consulting Engineers for the Project. The Project will rehabilitate approximately 9,087 linear feet of existing 6-inch and 8-inch diameter sewer mains and access structures deteriorated by hydrogen sulfide that were identified in the 2015 Wastewater Collection System Master Plan (Plan).
BACKGROUND
The Wastewater Management Division maintains approximately 1,560 miles of sewer collections and conveyance pipes and 25,580 access structures. To ensure the reliability of this extensive pipe network, annual rehabilitation projects are required. The sewer infrastructure was identified in the 2015 Plan for rehabilitation due to structural deficiencies of the pipe based upon Closed Circuit Television (CCTV) inspection performed by the City's Wastewater Collection System Maintenance Division. Through CCTV inspection, the existing 6-inch and 8-inch sewer mains were found to have deficiencies consisting of exposed aggregate within the existing standard concrete pipe and offsets, cracks in the vitrified clay pipe, and corrosion damage to the ductile iron pipe.
In accordance with Fresno Municipal Code Chapter 4, Article 1, and Administrative Order 6-19, the Department of Public Utilities conducted a competitive process to select a consultant to provide design services for the Project. A Request for Proposals was published in the Business Journal and posted on Planet Bids on November 18, 2020, inviting proposals for design, bidding support and construction support services for the Project. The City received four proposal packages from qualified consultants on December 16, 2020. The selection committee members met and evaluated the proposals on December 23, 2020 with Blair, Church & Flynn Consulting Engineers ultimately selected as the firm with the most experience to provide the services. The services required by this Agreement will be completed by June 30, 2022 for an amount not to exceed $145,158 inclusive of a $10,000 contingency paid on a time and materials basis.
A standardized Consultant Services Agreement has been used in accordance with Administrative Order 4-4 and the consultant's Certificates of Insurance have been approved by the City's Risk Management Division. Upon approval by the City Council, the agreement will be executed by the Director of Public Utilities, or his designee.
ENVIRONMENTAL FINDINGS
By the definition provided in the California Environmental Quality Act (CEQA) Guidelines Section 15378, the award of this consultant services agreement for the design services does not qualify as a "project" for the purposes of CEQA.
LOCAL PREFERENCE
Blair, Church & Flynn Consulting Engineers is a local business pursuant to Fresno Municipal Code Section 4-109(b).
FISCAL IMPACT
There is no impact to the General Fund. This Project is located in Council Districts 1 and 7. This Project is identified in the Wastewater Management Division's five-year Capital Improvement Plan. Funds in the amount of $344,500 for this Project are budgeted in the Fiscal Year 2021 Sewer Enterprise Fund 40501.
Attachments:
Attachment 1 - Consultant Services Agreement
Attachment 2 - Vicinity Map