Legislation / ID16-061
WORKSHOP - Update on the Status of the Construction Contract for the Fulton Street Reconstruction Project. (Council District 3)
- Introduced by
- City Council
- Date
- Thu, Jan 14, 2016
- Result
- Thu, Jan 14, 2016
Full textv1
REPORT TO THE CITY COUNCIL
January 14, 2016
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
BY: RANDALL MORRISON, PE, Deputy City Engineer
Public Works Department
SUBJECT
..Title
WORKSHOP - Update on the Status of the Construction Contract for the Fulton Street Reconstruction Project. (Council District 3)
..Body
Attachment:
PowerPoint Presentation
Sponsors
- Public Works Department
History
| Date | Body | Action | Result |
|---|---|---|---|
| Thu, Jan 14, 2016 | City Council | PRESENTED | — |