REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: October 3, 2016
FROM: THOMAS ESQUEDA, Director
Public Utilities Department
BY: MICHAEL CARBAJAL, Planning Manager
Public Utilities Department
SUBJECT
..Title
Approve Southeast Surface Water Treatment Facility Project - Change Order No. 5
..Body
Attachment: Change Order No. 5
Sponsors
- Department of Public Utilities
History
| Date | Body | Action | Result |
|---|---|---|---|
| Mon, Oct 3, 2016 | City of Fresno Capital Projects Oversight Board | APPROVED | Pass |
Attachments
- 160823_SESWTF_CCO No 5_DRAFT.pdfscanned_image
- Change Order 4b.pdfscanned_image