Legislation / ID16-445
Approve Change Order #1 for $262,720 for Recycled Water Transmission Main Southwest, Project SW1A
- Introduced by
- City of Fresno Capital Projects Oversight Board
- Date
- Mon, Apr 18, 2016
Full textv1
REPORT TO THE CITY COUNCIL ENTERPRISE CAPITAL PROJECT OVERSIGHT BOARD
DATE: April 18, 2016
FROM: Thomas Esqueda, Director
Public Utility Department
SUBJECT
..Title
Approve Change Order #1 for $262,720 for Recycled Water Transmission Main Southwest, Project SW1A
..Body
RECOMMENDATION
Approve Change Order #1
Attachment: Change Order #1
Sponsors
- Department of Public Utilities