Legislation / ID17-1175
Approve Regional Transmission Main Segment A2 (RTMA2) Project - Change Order No. 1
- Introduced by
- City of Fresno Capital Projects Oversight Board
- Date
- Mon, Aug 21, 2017
Full textv1
REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: August 21, 2017
FROM: THOMAS ESQUEDA, Director
Public Utilities Department
BY: MICHAEL CARBAJAL, Planning Manager
Public Utilities Department
SUBJECT
..Title
Approve Regional Transmission Main Segment A2 (RTMA2) Project - Change Order No. 1
..Body
RECOMMENDATION
EXECUTIVE SUMMARY
BACKGROUND
ENVIRONMENTAL FINDINGS
LOCAL PREFERENCE
FISCAL IMPACT
Attachment: Change Order No. 1
History
Attachments
- RTM A2 CCO 1.pdfuntagged