REPORT TO THE CITY OF FRESNO CAPITAL PROJECTS OVERSIGHT BOARD
DATE: August 28, 2017
FROM: THOMAS ESQUEDA, Director
Public Utilities Department
BY: MICHAEL CARBAJAL, Planning Manager
Public Utilities Department
SUBJECT
..Title
Approve Regional Transmission Main Segment A2 (RTMA2) Project - Change Order No. 1
..Body
RECOMMENDATION
EXECUTIVE SUMMARY
BACKGROUND
ENVIRONMENTAL FINDINGS
LOCAL PREFERENCE
FISCAL IMPACT
Attachment: Change Order No. 1
History
| Date | Body | Action | Result |
|---|---|---|---|
| Mon, Aug 28, 2017 | City of Fresno Capital Projects Oversight Board | APPROVED AS AMENDED | Pass |
Attachments